Ghazeepore Road – Timeline for remaining road safety upgrade works

  • Timeline item 1 - complete

    Roundabout at Ghazeepore Rd / Monterey Drive

    July 2025 - Sept 2025

  • Timeline item 2 - active

    Indenting the bus bays along Ghazeepore Road

    Three of four indents currently completed

  • Timeline item 3 - active

    Indented bus bay north of Monterey Drive

    Wednesday Sept 17 - Wednesday 01 Oct 2025

  • Timeline item 4 - incomplete

    Remaining indented car parking bays

    Works will recommence December 2025 - (once Rossack Drive works are completed)

  • Timeline item 5 - incomplete

    Single speed hump and bend control works near the childcare

    December 2025 (once Rossack Drive works are completed)

Feedback update

Thank you to everyone who provided feedback on the Ghazeepore Road traffic flow and pedestrian upgrades.

The below update shows:

  • Feedback summary from the community provided on the design plans
  • How we are addressing your feedback
  • Updated design plans showing the changes based on your feedback

Works are expected to commence 01 July 2025. Residents will be provided further updates on timing of works via letter from our construction unit.

Ghazeepore Road feedback summary from community:

.

How we are addressing community feedback:

Click the plans below to see the final design, inclusive of changes:

Any changes made to the previously displayed design plans are highlighted with a red box.

Ghazeepore Rd - Childcare centre - Number 30

Ghazeepore Rd - Colac Rd to Monterey Drive, Waurn Ponds

Click to enlarge the image

Ghazeepore Rd - Number 30 - Number 76

monterey to 167

Click to enlarge the image

Ghazeepore Road - Number 76 - Number 116

Ghazeepore Rd - Oakwood Cres to No. 113

Click to enlarge the image

Ghazeepore Road - Number 116 - Hams Road

113 to Hams

Click to enlarge the image


Project Background

We have been listening to the community's feedback and concerns raised in relation to traffic flow and pedestrian safety along Ghazeepore Road, Waurn Ponds over the past five years and have been planning works to address community concerns.

We have analysed community feedback submitted via:

  • objections to the Hams Road development that made reference to Ghazeepore Road, Waurn Ponds
  • traffic concerns submitted to City of Greater Geelong in relation to Ghazeepore Road and side streets.

The most common concerns raised by the community are shown below:

We’re now able to deliver a roundabout at Monterey Drive / Ghazeepore Rd intersection thanks to a $313,000 investment through the Victorian Government via the Safe Local Roads and Streets Program.

How we plan to address your concerns:


Who's funding these works?

We’re now able to deliver the roundabout at Monterey Drive / Ghazeepore Road intersection thanks to a $313,000 investment through the Victorian Government via the Safe Local Roads and Streets Program.
Edit


Oliver Hume Property Funds & HR Waurn Ponds Developer Pty Ltd (the developer of the Hams Road estate), has also contributed $500,000 to the City of Greater Geelong to assist with upgrade works along Ghazeepore Road, Waurn Ponds, as part of their Hams Road development. These funds will be used to deliver the proposed indented bus bays and parking bays, pedestrian refuges at key locations and new footpaths to fill the missing links.

The remaining costs required to cover the upgrades will be funded by City of Greater Geelong.

View the planned upgrades below:


Ghazeepore Rd - Eden Court to Grange Park Drive, Waurn Ponds

ghazeepore rd

Click to enlarge the image

Ghazeepore Rd - Grange Park Drive - Brentwood Way, Waurn Ponds

Ghazeepore Rd

Click to enlarge the image

Ghazeepore Rd - Brentwood Way - Hams Rd, Waurn Ponds

Brentwood Way - Hams Rd

Click to enlarge the image

The personal information and feedback (collectively the Data) requested on this page is being collected by City of Greater Geelong (City) for the purpose of Ghazeepore Road, Waurn Ponds - Road Safety Upgrades project, and any other directly related purpose (Project).

A de-identified engagement summary report may be published on our website.

If your personal information is not collected, the Project may not be able to be adequately conducted, and the City may not be able to contact you for further questions or to find solutions.

In order to collect and conduct in depth and detailed analysis of the Data for the purposes of the Project, the City will disclose the Data (including your personal information if provided) to its third-party service providers, including Social Pinpoint Pty Ltd, Converlens Pty Ltd and Amazon Web Services.

Other than as stated above, your personal information will not be disclosed to any external party without your consent, except as required or authorised by law

Our privacy policy is available on our website. If you wish to alter any of the personal information you have supplied to the City, please contact us by sending an email to privacy@geelongcity.vic.gov.au.


Contact Us

Have questions or want to learn more about a project, contact us below:

Contact Information
Name Zoe Smith – Senior Transport Engineer
Phone 5272 5272
Email contactus@geelongcity.vic.gov.au

I need assistance

The National Relay Service is available as a phone solution for people who are deaf or have a hearing or speech impairment.

To have content on the page read aloud to you, select text and click the listen icon that appears.

If we can assist any other way to help you provide your feedback please contact the project officer below.

This page is available in languages other than English.

To change the language click the button at the top right corner of this page and select your preferred language.

If you need an interpreter, call 131 450 or visit the Translating and Interpreting Service website for more information.